Acceptance Procedure:

Seaport Environmental does not charge a profile fee. In order to have waste accepted at the facility download, complete and fax to us a Waste Characterization Form which describes the source of the waste and lists possible contaminants. Seaport Environmental will wish to review any analytical work that has been carried out on the waste to ensure that it meets Seaports' acceptance criteria (check your waste is non-hazardous and does not exceed the listed values). Additional analytical work may be required at this point.

Upon acceptance Seaport will issue an approval number and require the generator to certify the waste is non-hazardous before receiving the waste at the facility. Seaport will provide a Non-Hazardous Water Transport Form for the transportation of the waste to Seaport's facility.

Seaport's facility is open 24 hrs a day 7 days a week.

 